Monday, February 26, 2007
Friday, February 16, 2007
Sunday, February 11, 2007
Most of the work was inside!
Not such a different picture from the outside, but a great deal of work was going on in the building. The upstairs partitions are now up; we've made a number of small design changes to improve the layout; and the walls are traced out ready for the electrics. External plastering is under way and the windows are expected soon!
Friday, February 02, 2007
Candlemas

Candlemas Day is bright with sun (!) marking the end of a great week of weather. There has been progress all over the site, inside and out. The roof line is clearly visible now, walls are being prepared for plaster and the new wall erected along our boundary. The windows are on order; and the first floor is marked up for partitioning. With fingers crossed, we've chosen the final external colours. Now on to the electrics!